RED Engineering is a trusted engineering partner for clients around the world who operate in hazardous conditions. They were approached by Sellafield to help them develop a solution to protect radiation workers from floor-based historical contamination, as part of their decommissioning activity.
Sellafield’s decommissioning activity is a multi-decade project to clean up the nuclear site, dealing with hazardous materials, untreated waste, and contaminated buildings. Workers on the site are carefully monitored for radiation exposure levels. The floor tile product will help to lower the radiation levels the decommissioning teams are exposed to in their areas, and prolong allowable working times.
The requirements for Sellafield were very specific. The product had to be:
- Easily deployable to and removable from a working area
- Light enough for manual handling by an individual – <25kg
- Equivalent to 5mm thickness of lead
- Capable of supporting an operator’s weight
- Easy to clean, with a smooth surface and no areas which could harbour contamination
Additionally, the pieces had to overlap, to ensure there were no gaps in the radiation shielding provided. All lead material needed to be fully enclosed in stainless steel metalwork to avoid direct contact with the operator.
There was also an additional specification – to try and avoid welding as much as possible.